Algeria phosphate project update, 2027 supply timing remains optimistic

29 September 2026

Algeria

In Brief

  • Three launch ceremonies: Algeria held ceremonies on 23–24 September for the Annaba port installations, Oued Kebrit fertiliser complex and Bled El Hadba extraction and enrichment complex.

  • Planned fertiliser capacity: Phase 1 comprises 2.4 Mt/y of phosphate fertilisers and 570 kt/y of urea, a combined 2.97 Mt/y of nameplate capacity.

  • 2027 targets: The August timetable envisaged initial enriched-phosphate production in Q1 and fertiliser production starting in Q4. A separate presidential instruction set March 2027 as the latest deadline for starting Bled El Hadba phosphate exports.

  • Contract status: Saipem disclosed an approximately €500m limited notice to proceed in August. AFRIQOM has not identified a subsequent public announcement confirming full EPC finalisation.

  • Infrastructure deadlines: Technical rail trials on 127 km were targeted for early October, subject to remaining works. Industrial-water connections were ordered complete before end-2026.

  • AFRIQOM assessment: Public disclosures do not yet provide sufficient evidence to support confidence in the Q4 2027 fertiliser production-start target. The ceremonies provide no basis to bring forward supply assumptions.


Algeria’s PIP update

Algeria held launch ceremonies for three components of its integrated phosphate project on 23–24 September, underlining official commitment to the programme. The previously announced 2027 production targets remain subject to delivery of the processing plants, utilities and export infrastructure.


The port-installations package at Annaba was launched on Wednesday 23 September, according to APS. Cornerstone ceremonies followed on Thursday 24 September at the Oued Kebrit fertiliser complex in Souk Ahras and the Bled El Hadba extraction and enrichment complex near Bir El Ater, according to Algérie Eco. 


Minister of State and Minister of Hydrocarbons Mohamed Arkab attended alongside public works minister Abdelkader Djellaoui and mines minister Mourad Hanifi. Algérie Eco’s 24 September report identifies Saipem as the contractor for Oued Kebrit under the announced EPC Fast Track approach, with Sonatrach subsidiaries SARPI, GCB and GTP participating. CHEC holds the Annaba port-installations contract; related port works also involve a consortium including CHEC, Cosider Travaux publics and the national Mediterranean maritime-works company. The reports do not provide a complete division of responsibilities between the port packages. 


The contractual distinction remains important. Sonatrach described the agreements announced on 12 August with Saipem and CHEC as two EPC contracts. Saipem's own disclosure described its instrument as an approximately €500m limited notice to proceed, pending negotiation and finalisation of the full EPC agreement. AFRIQOM has not identified a subsequent public announcement confirming that finalisation. The launch ceremonies do not resolve the difference between the two disclosures. 


The published Phase 1 specification provides for 5.5 Mt/y of raw phosphate extraction and 3.2 Mt/y of concentrate at Bled El Hadba. Oued Kebrit is designed for 2.4 Mt/y of phosphate fertilisers and 570 kt/y of urea, giving combined finished-fertiliser nameplate capacity of 2.97 Mt/y. September reporting restated these fertiliser capacities. They represent planned annual capacity, rather than expected output or export volumes in 2027.


TSA reported on 14 August 2026, quoting Arkab at the 12 August signing ceremony, that the timetable targeted initial enriched-phosphate production in Q1 2027 and the start of fertiliser production in Q4 2027. Separately, President Abdelmadjid Tebboune instructed in April that exports from Bled El Hadba should begin by March 2027 at the latest. These are announced targets. The September launch reports reviewed did not provide a detailed commissioning sequence or establish when the complete Phase 1 slate would reach sustained commercial production.


Supporting infrastructure remains a delivery dependency. TSA reported on 9 September, citing ANESRIF, that 174 km of the 422 km eastern mining railway programme had been completed. Separately, the public works minister called for remaining work to be finished on three sections totalling 127 km ahead of technical trials planned for the first week of October: Annaba–Bouchegouf, 54 km; Tébessa–Tanoukla, 43 km; and Drea–Oued Kebrit, 30 km. Those sections were approaching completion when the instruction was reported. Planned trials do not establish an operational freight corridor.


Industrial-water connections were also ordered to be completed before end-2026. Reported scope includes 157 km of piping and seven pumping stations for Bled El Hadba, and 78 km of piping with a pumping station designed for up to 1,200 litres/second at Oued Kebrit. 


Sonatrach names Algerian Fertilizers Company, AFC, in its current project announcement. Its legal relationship to the earlier Algerian-Chinese ACFC vehicle was not explained in the launch reports reviewed. Historical ownership and investment figures therefore require separate treatment: the approximately US$7bn estimate reported in 2022 is not a verified current Phase 1 budget. 


AFRIQOM view

This is major new fertiliser complex with multiple different downstream projects and these take time. The public evidence does not yet support confidence in the announced timetable. For a project of this scale and complexity, the disclosures reviewed by AFRIQOM provide insufficient detail on construction progress, equipment delivery and commissioning to substantiate the Q4 2027 fertiliser production-start target. That remains the authorities’ target; it is not an established date for the project completion.


Indeed, the September ceremonies reinforce official intent. They do not, however, establish an acceleration in physical execution or resolve the dependencies across processing facilities, rail, water and port infrastructure. Documented delivery and commissioning milestones are needed to support a stronger assessment.


Earlier mine activity provides evidence of preparation, with beneficiation readiness still unproven. An APS report carried by Radio Algérienne on 20 June 2026 described mine preparation under way since October 2024. That does not establish that treatment facilities and utilities will be ready for enriched-phosphate production in Q1 2027. Export availability also depends on functioning handling and transport links.


The downstream schedule requires a clearer execution record while the project engineering predates the September ceremony: Saipem announced its front-end engineering and design award on 19 June 2025 under a competitive dual FEED process. The public record reviewed does not establish a first-concrete date or a unit-by-unit startup sequence. It cannot substantiate a confident forecast that the announced production-start target will be met. 


AFRIQOM sees no basis to bring forward supply assumptions. The planned 2.97 Mt/y of fertiliser capacity should not be treated as available output in 2027. Full EPC finalisation, documented process-unit delivery and a credible commissioning sequence across the mine, plants, utilities and export chain would support a stronger assessment.

Algeria phosphate project update, 2027 supply timing remains optimistic

AFRIQOM Market Reporter

AFRIQOM Insight 2.png
AFRIQOM logo

Leader in Fertilizers Price Reporting, Market Data and Business Intelligence in Africa.

Contact

Follow us on social media

AFRIQOM LinkedIn
AFRIQOM Youtube
AFRIQOM X
AFRIQOM Facebook

Casablanca:   +212 520 002 083

Dubai:              +971 (0) 4 448 7288

Casablanca:   +212 669 466 727

© 2025 AFRIQOM. All Rights Reserved.

bottom of page