In Brief
Algeria has moved Phase 1 of its Integrated Phosphate Project further into execution, covering mining, beneficiation, fertiliser production and export infrastructure.
Phase 1 targets 3.2mn t/y of phosphate concentrate, 2.4mn t/y of phosphate fertilisers and 570,000 t/y of urea.
Saipem has signed a ~€500mn limited notice to proceed, allowing engineering, early procurement and mobilisation while the full EPC contract is finalised.
Authorities target enriched phosphate production from Q1 2027 and fertiliser output from Q4 2027. AFRIQOM considers the upstream target more plausible, while the downstream timetable remains highly ambitious.
Integrated phosphate project advances
Sonatrach and Algerian Fertilizer Company (AFC) signed agreements with Italy's Saipem and China Harbour Engineering Company (CHEC) on 12 August covering key components of Phase 1 of Algeria's Integrated Phosphate Project.
The programme integrates phosphate extraction and beneficiation at Bled El Hadba in Tébessa, downstream transformation and fertiliser production at Oued El Kebrit in Souk Ahras, and export infrastructure through the port of Annaba.
The wider project has previously been valued at around US$7bn.
Sonatrach described the latest instruments as EPC contracts. Saipem, however, separately confirmed that its current agreement is a Limited Notice to Proceed worth approximately €500mn, ahead of finalisation of the full EPC contract.
The LNTP allows Saipem to complete FEED, progress detailed engineering, begin procurement of long-lead equipment and undertake preliminary mobilisation.
Saipem had previously secured the project's competitive FEED assignment in June 2025.
CHEC expands existing Annaba role
CHEC is not a new contractor at Annaba. The Chinese engineering group is already engaged on the Annaba mineral quay under a February 2024 consortium contract with Cosider Travaux Publics and Meditram, covering expansion of the mineral terminal and associated marine works. Those works are already in execution.
CHEC has now taken an additional Phase-1 port infrastructure package commissioned by Sonatrach. The Chinese contractor separately disclosed a 36-month EPC construction period covering six loading and unloading berths, railway handling stations, storage areas, cargo-handling systems and supporting infrastructure.
The distinction is important. The mineral-quay works awarded in 2024 could allow initial phosphate exports through earlier-completed infrastructure while the wider Phase-1 logistics and handling system continues to be built out.
Phase-1 capacities
Official disclosures put Phase-1 capacity at:
Raw phosphate extraction: 5.5mn t/y
Phosphate concentrate: 3.2mn t/y
Phosphate fertilisers: 2.4mn t/y
Urea: 570,000 t/y
The first phase therefore represents close to 3mn t/y of finished fertiliser capacity, alongside intermediate production including sulfuric acid, phosphoric acid and ammonia. At full development, Algerian authorities envisage around 10mn t/y of raw phosphate processing, 6mn t/y of enriched phosphate and around 4mn t/y of finished fertilisers across DAP, MAP, NPK and urea.
Algeria targets 2027 start-up
Algerian authorities are pursuing the project under an accelerated EPC Fast Track programme. The official schedule targets first quantities of enriched phosphate from Q1 2027, while President Abdelmadjid Tebboune has instructed that phosphate exports from Bled El Hadba begin by March 2027. Initial fertiliser production is targeted from Q4 2027.
The dates, however, should be distinguished from commercial ramp-up of the full integrated system.
AFRIQOM View
The latest agreements materially advance one of Africa's largest new fertiliser projects and provide much greater clarity on Algeria's intended Phase-1 production slate. But AFRIQOM considers the official 2027 commissioning timetable highly ambitious, particularly for downstream fertiliser production.
Mining, railway and mineral-quay infrastructure have been progressing separately from the newly activated downstream package. This creates a credible pathway for Algeria to bring initial phosphate or concentrate tonnes to market before the entire fertiliser complex is commissioned.
The Q4 2027 fertiliser target carries considerably greater execution risk. As of 12 August, Saipem's full EPC contract remains under finalisation, while detailed engineering, long-lead procurement and mobilisation are only now progressing under the €500mn LNTP. The downstream development is also substantial. Phase 1 encompasses 2.4mn t/y of phosphate fertilisers and 570,000 t/y of urea, supported by sulfuric acid, phosphoric acid and ammonia production.
Moving from the present engineering and procurement stage to first finished-fertiliser production within roughly 14-16 months is a monumental task with no preceding successful project in Algeria meeting those timelines.
The logistics chain adds another layer of complexity. CHEC's newer Sonatrach-linked Annaba package carries a 36-month construction period, meaning parts of the fully integrated export system will continue to be developed beyond 2027. This does not necessarily prevent initial phosphate exports, given the earlier mineral-quay works already under execution. It does, however, reinforce the distinction between first tonnes and a fully integrated mining, processing, fertiliser and export system operating at commercial scale.
AFRIQOM therefore views Q4 2027 primarily as an initial-production target, and questionable, rather than an indication that the full Phase-1 fertiliser capacity will be commercially ramped up by then. Even if first finished tonnes are achieved within the official timetable, sustained production approaching the nearly 3mn t/y Phase-1 nameplate capacity would require successful commissioning and integration across the mine, beneficiation facilities, chemical intermediates, fertiliser units, railway and port infrastructure. This is a monumental task, and a major project to tackle.
This is AFRIQOM's assessment and not an official revision to Algeria's project schedule.
If delivered, even on a slower ramp-up than currently targeted, the project would materially expand Africa's phosphate-fertiliser production.
What to watch
Saipem full EPC: timing, final value and scope following the ~€500mn LNTP.
Oued El Kebrit mobilisation: evidence of major civil works and arrival of long-lead equipment.
Q1 2027 phosphate target: whether Bled El Hadba achieves initial enriched-phosphate production and exports by March.
Q4 2027 fertiliser target: whether the timetable remains intact as downstream engineering and construction progress becomes clearer.
Annaba infrastructure: sequencing between the existing mineral-quay works and CHEC's additional 36-month Phase-1 port package.
Rail integration: progress on the Eastern Mining Railway relative to mine, processing and export commissioning.
AFC / ACFC structure: clarification of the relationship between AFC and the previously established ACFC project vehicle, including the role of Chinese partners.
Financing: the current funding structure for the wider programme, previously valued at around US$7bn.
Sources: Sonatrach · Saipem · APS · CHEC · AFRIQOM research

AFRIQOM Africa Fertiliser Capacity Pipeline Alerts

